Fairfield Project Milestones
Created by kevin on 18 Jan 2008 | Tagged as: Fairfield Residential
These Project Milestones were taken directly from the poster Fairfield Residential prepared for the Open House they presented at Milliken School on 15 November 2007. A digital photograph taken of the poster can be found here.
| Project Milestones | Scheduled Start | Scheduled End | Comments |
|---|---|---|---|
| Physical Testing/Site Due Diligence | Summer ‘07 | Claimed complete | |
| Preliminary Site Concept Plans | August ‘07 | November ‘07 | Complete |
| Present Concept Site Plan/Open House | November ‘07 | Complete | |
| File Entitlement Application with City | December ‘07 | Complete | |
| Begin Environmental Impact Report (EIR) | December ‘07 | Started Jan. ‘07 | |
| City Review of Application | December ‘07 | July ‘08 | In Progress |
| Demolition of Hospital | Spring ‘08 | Possibly delayed | |
| Draft EIR Available for Public Review/Comment | July ‘08 | August ‘08 | |
| Public Hearing: Planning Commission | September ‘08 | October ‘08 | |
| Public Hearing: City Council | October ‘08 | December ‘08 | |
| Design Review | December ‘08 | March ‘09 | |
| Site Grading/Infrastructure work | Summer ‘09 | ||
| Construction Duration | Summer ‘09 | Summer ‘11 |
Leave a Reply
You must be logged in to post a comment.