These Project Milestones were taken directly from the poster Fairfield Residential prepared for the Open House they presented at Milliken School on 15 November 2007. A digital photograph taken of the poster can be found here.

Project Milestones Scheduled Start Scheduled End Comments
Physical Testing/Site Due Diligence Summer ‘07   Claimed complete
Preliminary Site Concept Plans August ‘07 November ‘07 Complete
Present Concept Site Plan/Open House November ‘07   Complete
File Entitlement Application with City December ‘07   Complete
Begin Environmental Impact Report (EIR) December ‘07   Started Jan. ‘07
City Review of Application December ‘07 July ‘08 In Progress
Demolition of Hospital Spring ‘08   Possibly delayed
Draft EIR Available for Public Review/Comment July ‘08 August ‘08  
Public Hearing: Planning Commission September ‘08 October ‘08  
Public Hearing: City Council October ‘08 December ‘08  
Design Review December ‘08 March ‘09  
Site Grading/Infrastructure work Summer ‘09    
Construction Duration Summer ‘09 Summer ‘11